Schedule an Automation
Use a schedule to start an Automation at a recurring time. Each scheduled Run opens a Board Session in the project’s main checkout.
Set the schedule
Section titled “Set the schedule”- In your project’s navigation, open Automations, then select New automation.
- In Name, enter a name you can recognize in a run menu.
- In Instructions, write the first message the new Session should receive.
- Under Trigger, select Schedule.
- Choose a Frequency:
- Hourly runs at a chosen Minute past each hour.
- Daily runs at a chosen Time each day.
- Weekdays runs at a chosen Time Monday through Friday.
- Weekly runs on a chosen Day and Time.
- Choose a Time zone. A new schedule starts with this Mac’s current time zone. The saved zone stays in effect if you travel.
- Choose a model under Runtime → Model, or leave Project default. Scope stays set to This project for schedules.
- Select Create.
- In the saved Automation’s Trigger section, turn on Automatic triggers on this Mac.
The enabled Automation’s header shows Next with its next due time in the saved time zone. To change a schedule, select Edit beside Trigger. Next runs previews three upcoming times in that zone. Select Save to apply the change. Turning Automatic triggers off removes the header’s next due time and pauses future automatic starts.
Timing and availability
Section titled “Timing and availability”Schedules use these four presets; they do not accept cron expressions. Volli must be running and the Mac awake to start work on time.
Schedules set to minute 00 have a stable delay of less than five minutes so
they do not all start at once. The next-run times include that delay. Choosing
another minute avoids it. A running app can start a Run up to two minutes
after its computed due time; a later occurrence is skipped. Launching Volli
after a due time does not replay it, even within those two minutes.
Schedules follow the saved zone’s daylight-saving changes. If a chosen time does not exist during a spring-forward change, it runs later by the size of the clock change. If a time repeats during fall-back, Volli uses the later occurrence once.
Open Trigger more actions → Schedule policy beside Trigger for the short timing policy.
Handle a missed occurrence
Section titled “Handle a missed occurrence”If a due time passes while Volli is closed, or the Mac does not wake in time, history records a Skipped occurrence with its reason. A refused Run, such as one blocked by an earlier Run of the same Automation, also records the reason. Volli leaves the next occurrence on the saved cadence.
To start the work anyway, select Run now on the skipped row. This starts one project-level Run, even if the row covers several missed times. Enabling or retiming a schedule starts watching from that point; it does not create a backlog for earlier times or periods when automatic starts were off.
See Run history to open a Run’s Session. For column-based starts, see Arm a column Automation.